Monday, December 7, 2009

A finished roof and an update, finally

Copper roof repair, finished!

I haven't posted here in a while because there hasn't been much going on around the house. The roof repairs are done for this year. I'm really pleased with the job that Dennis Crookshanks did on the job. There was a large section of slate that showed evidence of several different repairs in the past. He replaced it with flat-seam copper and installed ice guards. He also replaced some of the slate on the breezeway and replaced the flashing there, too.

Copper Roof, finished!

The flat-seam copper really looks great.

Of course, now I'm seeing all the other flashing work that needs to be done - one project at a time, I guess. Given the build quality of the rest of the house, I'm surprised that they used galvanized flashing instead of copper.




There's another reason why I haven't posted on here in a while. I've been working on another project, Cleveland Area History. I've been writing about all sorts of things relating to the history of the greater Cleveland area. I toured the house where Langston Hughes lived during his sophomore and junior years of high school. I've talked about two of the oldest houses in the area, one in Cleveland Heights, the other in Cleveland. I've illustrated a National Register of Historic Places historic district. And there's more. Check it out.

Monday, November 9, 2009

Roof progress!

New copper roof section

I had assumed that Dennis Crookshanks wouldn't be able to start work on the roof until spring. Much to my surprise, I got an email last week saying that he would beginning shortly. He began replacing the slate in the trouble area with flat-seam copper, which should hold up better than the slate.

New copper roof section

The copper, it looks so pretty.

Tuesday, October 6, 2009

Midtown Roofing Supply - purveyor of copper goods for roof repair

Midtown Roofing Supply, at 2695 E 55th St, Cleveland, OH, 44104, (216-431-4545), is an unassuming brick building that you'd probably miss if you weren't looking for it. There are no windows and it only has parking for two or three cars. I certainly wouldn't have stopped there if not for the recommendation by the people at Sutton Industrial Hardware.

Midtown Roofing seems to be the best place in Cleveland to buy the various supplies and tools that one might need to work on a slate roof. This includes slate hooks, in both copper and stainless steel, copper for flashing and valleys, as well as the various tools, like slate hammers and slate rippers that are needed to work with slate.

They might have quite a bit more, too - I'm not sure - most of the stock was back in their storeroom, not out on display.

Monday, September 21, 2009

Avoid Paul David Plumbing for anything but plumbing!!

While he is a good plumber, he is horrible as a general contractor! (He also does business under the name "Feldman Mechanical Contractors" or "Feldman Mechanical Contracting".)

When we hired Paul David Plumbing as our general contractor, it was because Paul David had done good plumbing work at a reasonable price. He was willing and able to deal with the old plumbing in our house, and to do things like rebuild our 1920s toilets.

He has proven himself completely incapable as a general contractor. We paid the deposit for materials, about 65% of the total cost of the job, in April. The contract was entered into with the agreement that a subcontractor with experience in slate would be doing the vast majority of the work, and that Paul David would be doing some work to assist them.

Paul David Plumbing provided us with excuse upon excuse upon excuse why the work had not begun on the roof. Last week, Paul David himself began work on the breezeway between the house and the garage. When one side of the breezeway repair was complete, he asked if we were satisfied with how it looked - I was - but this was based on appearance only. There was another slate that he had replaced, with a nail driven through the face of the slate, which I infomed him was improper practice, and that such repairs needed to be done with a slate hook. Paul David was unable to locate a supplier of slate hooks, which should have been a warning.

Back dormer work done by Paul David

Next Paul David began work on the rear part of the roof, where there had been considerable damage from ice falling on it the previous winter, and where it was obvious repairs had been performed previously. The slate for the bottom few rows are 28 inches long. The slate installed was only 24 inches long, which did not provide sufficient overlap. Paul David did not realize this was an issue until it was pointed out to him. He further didn't realize that the slate needed to be shimmed out, using smaller pieces of slate, to fit the slightly curved framing of the roof.

It was at this point that we realized that Paul David Plumbing had failed to live up to their end of the contract. A professional with experience on slate had not been brought in, as had been specified in the contract. Further, slate adequate for the job had not been provided.

Back dormer work done by Paul David

When Paul David Plumbing informed us that the proper sized slate wasn't readily available, we told him that we expected the exposed area and the improperly slated area to be covered to prevent damage from rain, which is expected for the rest of the week. When it appeared, on Sunday, that it was going to rain, we called Paul David Plumbing, informing him of this, asking him to cover the area. He said that he'd try to be out that afternoon. When we called him again, an hour later, when rain was threatening, he said that he couldn't make it and that his insurance would just have to cover it.

That was the absolute last straw. While Paul David may be a competent plumber, he simply cannot be trusted with anything beyond that.

Breezeway work done by Paul David

On further inspection of the breezeway, in the area where work had not yet been completed, I saw that the slate was not installed properly - the nail holes in the slates were not countersunk, so the nail heads will rub against the slate above, eventually wearing through. Further, the flashing at the house is in such poor shape that it really should be replaced. This was not part of the original contract, but something that should have been brought to our attention - it makes little sense to repair the slate now, only to have to take it off in a couple years to redo the flashing.




I took a very long lunch today (and as a result will be working quite late tonight) and met with Paul David to iron out the details of the completion of the contract. By next Friday, he will present us with a list of all the money that has been spent on materials, which will be deducted from the amount we paid, in April, for materials. From his costs will be deducted the cost of a temporary repair on the main roof of the house and repair of the improper work done on the breezeway. If he doesn't provide us with the expenses by next Friday, the amount will be assumed to be $2000. Either way, the amount due back to use will be paid in full by two weeks from that Friday.

I'm not terribly confident that we'll get our money back, but at least now we have everything in writing, and we have some legal standing, I hope.

In good news, Dennis Crookshanks (of Dennis M. Crookshanks Const., Inc.), whose gallery features some pretty impressive work, will be at our house either today or tomorrow to evaluate the situation and install a temporary patch. He clearly knows his stuff - I only wish I'd gone with the estimate that he'd provided when we called him originally. Fortunately, he still has our information on file, so it shouldn't take him terribly long to write up.

Friday, September 18, 2009

Disappointment

We are presently looking to see what our options are for pursing legal action against Paul David Plumbing. He has failed to deliver on the projects that he was contracted to complete, namely repairs to the roof, the chimney, and our gutters, supplying us with excuse after excuse after excuse.

He had said (and I should have specified further in our contract) that he had talked with a roofing firm who was to repair our roof and that he would only act as assistant. Now, with excuse after excuse, he's begun the work on the roof, himself. First he completed some work on the breezeway, which acceptable. Then he began to work on the main roof of the house. The slates that he had ordered were not long enough for the job, but he did not realize that. As a result, as installed, they do not have sufficient overlap. Further, the framing of our roof curves out, and the proper slate shims were not installed to avoid stress upon the slate.

This guy doesn't know what he's doing. He's taking forever. Right now, there's a big open chunk on our roof and we're screwed.

I bring up these issues and he just comes up with one excuse and then another. It's always going to be done in just a couple days, just a couple days more.

I just don't know how to handle all this. I'm freaking out because I feel I have no options. I'm not going to be able to meet the deadlines that the city has set for addressing the violations on the house, and I'm going to have a big hole open on my roof all winter.

On the plus side right now, and this is really the only thing on the plus side, the first gutter that was sent out to be repaired was returned today, and looks great. The gutter is copper, and they were able to roll out all the dents, thus that it looks like the rest of the gutters, or perhaps a bit better.

Monday, April 20, 2009

Finally, an update!

There's been a fair amount of work being done on our house recently, unfortunately, most of it is the sort of stuff that doesn't lend itself terribly well to photography.

We had the previously-discussed plumber provide us with an estimate regarding items on the city point-of-sale inspection as well as a considerable amount of work with regard to our radiators. Many of the radiators, you see, have valves that either don't open, don't close, or are leaking. Further, many of the bleeder valves won't bleed. A couple of the radiators, in the attic, didn't have shut-off valves at all.

His estimate seemed very reasonable, so we decided to go ahead with the work. When I did a final walkthrough with the plumber before he ordered the parts and began the work, we found a few more valves that needed to be fixed, as well as several bleeders that didn't bleed. He said that he could get all of this done, at the price he had estimated originally.

There was some additional work required - the baseboard radiators in the library had to be replaced, as they didn't have a hot-water return line, and had become clogged. This was done at reasonable material cost.

The entire time, the plumber kept us well informed of his progress, consulting us at each step along the way where decisions of aesthetics might be involved. He is quite comfortable dealing with the issues involved with older plumbing systems.

As this work was nearing completion, we had talked about the repairs that I hope to have done on the roof. I thought that the plumber might know someone who could do the repairs on the roof at more reasonable rates, given that his rates were lower than what I might have expected. He talked to a roofer with considerable experience with slate and came up with an estimate considerably lower than the other estimate I received. The plumber would act as the general contractor and would be doing some of the basic work on the job. His estimate was such that it seems we'll be able to get almost everything done this year!

I came up with a diagram of all of the areas of damage that I saw on the roof and discussed this with the plumber. On Sunday, we went over everything again, including my specifications, and I wrote him a check for the cost of materials. He's begun assembling materials and tools in the garage and will begin work on the roof on Wednesday, if weather permits.

I'll be sure to keep posting as the work progresses.

Friday, March 6, 2009

My brilliant neighbor

My neighbor's house

I've always liked wood shake roofs. The problem with them is that they cost about as much as slate, yet have the lifespan closer to that of asphalt shingles. They do, however, look stunning, especially when crafted to look like thatch.

My next door neighbor (or perhaps his contractor) had an idea that I wish I could take credit for. If it's ok to paint wood shingles on the walls of your house, why not paint the wood shingles on the roof? (I don't think he chose the best color, but that's another matter.) While the visual effect isn't quite the same as the unpainted shingles, I think it's a better compromise than ripping them off and replacing with asphalt. With regular painting, I assume that they will last as long as any other exterior wood.

More roof photographs

Front of the house
I actually got some decent looking photographs of the roof yesterday. This one happens to illustrate the chimney and a couple broken slates as well.

Gutter detail, south side of house
This is the area behind the gutter. Note the utter lack of paint. This appears to be the case all the way around the house. Note also that the gutters are soldered together at the seams, which will make removing them somewhat difficult. Ugh.

Entryway ridge
This illustrates why it is not a good idea to use aluminum for ridges on slate roofs. Copper or galvanized steel is sturdier.

Weird overlap pattern?
Finally, here's something that I just don't understand at all. If you look at this picture, you'll see, in the first row of slates, two slates that have a wider gap than might normally be expected. In those gaps, you can see what appears to be a short slate. This does not make sense to me. Kurt? Anyone?

IMGP6626
Here's a slightly better detail. It occurs in several spots on this, the west side of the roof, across several rows. I can't imagine that these are the result of broken slates being repaired, but I can't think of anything else that it might be, either. Surely there's something that I'm missing here.

Thursday, March 5, 2009

Oh where, oh where has my cricket gone?

Fireplace chimney

I knew when we bought this house that there should be a cricket to divert the water around the chimney here. You can't see it in the photograph, but the chimney is about 3-4 feet wide. Thus, there's quite a bit of water hitting it when it rains - and some of that water is leaking in.

Today, I climbed the extension ladder to investigate the condition of our roof.

Missing cricket
And then...

Missing cricket
The site of the missing cricket.

It seems that there was a cricket to divert the water around this chimney, but at some point in the past, some idiot, likely the one who installed this lovely bit of flashing, removed it. Meh.

If there's a reason why this would be a good thing, please, let me know.